Final Comment
The SAHRA has no objections to the submitted report. The following applies and must be included in the EMPr:
38(4)b – The recommendations of the specialists are supported and must be adhered to. Further additional specific conditions are provided for the development as follows:
All identified heritage resources recommended for avoidance must be avoided with a 30 m no-go buffer;
A Heritage Management Plan must be developed for the management of all identified heritage resources. The HMP must be submitted to SAHRA for comment prior to the construction phase;
38(4)c(i) – If any evidence of archaeological sites or remains (e.g. remnants of stone-made structures, indigenous ceramics, bones, stone artefacts, ostrich eggshell fragments, charcoal and ash concentrations), fossils or other categories of heritage resources are found during the proposed development, SAHRA (Natasha Higgitt 021 202 8660/ [email protected]) must be alerted as per section 35(3) of the NHRA. Non-compliance with this section of the NHRA is an offense in terms of section 51(1)e of the NHRA and item 5 of the Schedule;
38(4)c(ii) – If unmarked human burials are uncovered, the SAHRA DAU (Natasha Higgitt 021 202 8660), must be alerted immediately as per section 36(6) of the NHRA. Non-compliance with this section of the NHRA is an offense in terms of section 51(1)e of the NHRA and item 5 of the Schedule;
38(4)d – See section 51 of the NHRA regarding offences;
38(4)e – The following conditions apply with regards to the appointment of specialists:
With reference to the mitigation work noted above, a qualified archaeologist must be appointed to undertake the work in terms of the permit applied for as noted above;
If heritage resources are uncovered during the course of the development, a professional archaeologist or palaeontologist, depending on the nature of the finds, must be contracted as soon as possible to inspect the heritage resource. If the newly discovered heritage resources prove to be of archaeological or palaeontological significance, a Phase 2 rescue operation may be required subject to permits issued by SAHRA;
The Final EMPr must be submitted to SAHRA for record purposes.