CaseDetails
Summary
Case ID
3433
Case Status
Official Reference
16/1/3 Solar Aries Power Lines
Proposal Description
EIA, WULA and EMPr for the proposed Solar CSP Integration Project: Project 1 - Solar Substation, 2 x 400kV Power Lines from Aries to the Solar Substation and 400kV Power Line from Nieuwehoop to the Solar Substation
Post date
13/09/2013 - 14:40
Last modified
04/11/2024 - 09:18
Reports
HIA Phase 2 | Aries – Upington 400kV Line, Northern Cape Province | Jaco van der Walt | download, download | |
Conservation Management Plan for the Eskom 400kV Line from Aries to Upington | Edward Matenga | download, download, download |
Official Use
Official
Case Officers
Location
Location
RoDs/Permits
Decisions, Comments + Permits
Decision Date | Type | |
---|---|---|
Final Comment | Access Document | |
Final Comment | Access Document | |
Final Comment | Access Document | |
Interim Comment | Access Document |