The SAHRA, Development Applications Unit (DAU) acknowledges the submission of the S24G (EIAR) and the PIA report.


However, the SAHRA requests that the heritage assessment of the impacts to heritage resources that complies with section 38(3) of the NHRA as required by section 38(8) of the NHRA and section 24(4)b(iii) of NEMA be conducted as part of the EA process. A field-based assessment of the impact to archaeological resources must be conducted by a qualified archaeologist. The report must comply with section 38(3) of the NHRA and the SAHRA 2006 Minimum Standards: Archaeological and Palaeontological Component of Impact Assessments, and the 2012 Minimum Standards: Archaeological Component of Heritage Impact Assessments. 

The Minimum Standards provides allowance for a Letter of Recommendation for Exemption that can be submitted by a qualified archaeologist should they deem it appropriate. The applicant is advised to extend the EA process in terms of section 19(1)b of the NEMA EIA regulations in order to address this comment. Further comments will be issued upon receipt of the above requested report.